Receive email notifications by changing your settings.
Click on your picture in the top right corner, go to Preferences and select your notification preferences.
Click on your picture in the top right corner, go to Preferences and select your notification preferences.
Thank you for contributing to our forum!
Please keep in mind:
1. To only comment on the topic where the discussion is about. Do you have a new question or topic? Please start a new discussion.
2. Be kind to other users!
Please keep in mind:
1. To only comment on the topic where the discussion is about. Do you have a new question or topic? Please start a new discussion.
2. Be kind to other users!
Test run not ending
After adding actions in the future design, the test run stays activated. Hence, I can't work further on the actions because I have to end the test run and then the actions I've added are removed. How can I add actions and keep them?
Comments
Hi @Hogeschool_rotterdam 3 ,
If you implement actions and measures, you will start a test run. In case you want to edit actions or measures, you will have to stop the test run. In order to be able to reproduce actions exactly each test run, we advise you to design them as measures. This way you can implement te same plan/ measure each test run, while you adjust, for example, indicators or overlays.
In case you want to permanently change the default state of the project area, you should change the 3D area in Current Situation, by adjusting Buildings, Areas, etc. Please save before you make any definitive changes to the default situation, or use versions.
See also:
Future Design - Tygron Support wiki
https://support.tygron.com/wiki/Future_DesignCurrent Situation - Tygron Support wiki
https://support.tygron.com/wiki/Current_SituationTest Run - Tygron Support wiki
https://support.tygron.com/wiki/Test_RunI hope this helps,